RERA serves Rs 9.55 crore notice on Antriksh Realtech for non-compliance of its order in stalled Antriksh Sanskriti project

Ghaziabad, September 04, 2020: AntrikshRealtech Private Limited has been served a Rs 9.55 crore notice by the Uttar Pradesh Real Estate Regulatory Authority (UP-RERA) for violation of one of its orders in the long-delayed Antriksh Sanskriti group housing project on NH-24. As per the RERA notice a penalty of Rs 9.55 crore may be levied on Antriksh Realtech if it does not ensure timely compliance of this order.

It may be recalled that more than 1200 homebuyers who booked flats in Antriksh Sanskriti in 2010-11 are yet to get possession of their flats as the project that was to be completed by 2014 has been sealed by Ghaziabad Development Authority for non-payment of land dues running into Rs 42 crore. One of the homebuyers in this project, Vishal Goyal, who currently resides in Saket, New Delhi, had lodged a complaint in UP-RERA that the builder did not give possession of his flat even after 10 years. Taking cognizance of the matter UP-RERA had earlier issued an order that the allottee should be delivered possession papers by March 2020. Simultaneously the builder was ordered to pay interest to the tune of one per cent plus Marginal Cost of Funds Landing Rate (MCLR) to the complainant.  But Antriksh Realtech failed to comply with this UP-RERA order subsequent to which UP-RERA has issued this notice to the builder.

The homebuyers of Antriksh Sanskriti project have already paid around 90-95% of total committed value of the flats. Unfortunately, they are yet to get a roof over their head as the project is far from complete.

Corporate Comm India (CCI Newswire)

The Property Times News Bureau

Recent Posts

Define Affordable Housing Around What Smaller Towns Can Finance – Editorial by Khazi Altaf Hussain

20-November-2026: The National Housing Bank is consulting stakeholders on a separate affordable housing loan classification…

14 hours ago

Make the Cost of Temporary Relocation Visible Before Redevelopment-Editioral by Khazi Altaf Hussian

19-November-2026 Peninsula Land has signed a redevelopment project involving two housing societies in Mumbai’s Versova,…

2 days ago

Stalled Housing Projects Need Transparent Completion Plans-Editioral by Khazi Altaf Hussian

17-November-2026 The National Company Law Appellate Tribunal has directed that Ajnara India’s six housing projects…

4 days ago

Warehouse Growth Needs Sites That Work Beyond the Loading Bay – Editorial by Khazi Altaf Hussain

16- November-2026: Colliers reported on 11 November that industrial and warehousing space taken up across…

5 days ago

Mumbai’s Diwali Registrations Leave the Affordability Question Open – Editorial by Khazi Altaf Hussain

14-November-2026: Mumbai recorded 3,683 property registrations between 1 and 11 November, up from 3,668 in…

7 days ago