New Delhi, June 20, 2018: Project delays are one of the most alarming issues historically dogging the Indian real estate sector. The dearth of effective planning and execution of construction activities, escalating construction costs, approval delays, diversion of allocated funds to other projects and tepid sales are some of the predominant factors resulting in project delays. The homebuyer is, of course, at the losing end.
The National Capital Region (NCR), one of the country’s largest residential markets, was seriously wounded by sudden policy changes, structural reforms – and the dubious practices of unscrupulous developers. As a result, it topped the list of cities with maximum project delays. Around 1.5 lakh units in NCR missed the 2017 deadline. The story in Mumbai Metropolitan Region (MMR) was no different with nearly 1.1 lakh units missing the said deadline.
NCR: Where project delays are the order of the day
In NCR, out of the total 1.9 lakh units expected to be delivered in 2017, only 42,500 units were given for possession as promised. Approximately 49% (~73,000 units) of the undelivered residential units were in Greater Noida, followed by 17% (~25,300 units) inGhaziabad, 13% (~19,400 units) in Gurgaon and 11% (~16,000 units) in Noida.
In addition, a severe cash crunch due to syphoning of funds by developers for other projects, tweaked project details to bypass environmental/regulatory clearances, changing norms, water/sand crisis and red-tapism became some of the common causes of the long-delayed projects of NCR. Consumer sentiment was severely shaken by these delays and finally brought the sector to a standstill. Developers’ profits took a massive hit and their negative cash flows increased the delays even more.
Can NCRs developers beat the odds in 2018?
The above analysis talks only about the delayed projects that are anticipated to be delivered by the end of 2018. There is more to the story – namely the actually planned deliverables for the year 2018. Besides the delayed 79,400 units whose revised possession timelines are now December 2018, there are actually planned deliveries of around 86,600 units for this year. Altogether, NCR developers are expected to deliver around 1.66 lakh units (3.9 times the units delivered in 2017) by this year-end.
Will developers in NCR be able to deliver such a large number? That is certainly something that bears watching closely. With RERA expected to streamline residential real estate, homebuyers are hopeful that projects that have been stalled or slowed down over the years will pick up momentum and finally be delivered.
The Government authorities are certainly scrutinizing the issue by auditing long-delayed projects to chalk out initiatives and ensure their completion. All-in-all, with a massive number of residential units due for completion, year 2018 is a tough one for the NCR property market.
Corporate Comm India(CCI Newswire)
Brigade REAP Incubates 76 Proptech Startups, Leading India's Largest Proptech Ecosystem with ₹200 Cr Earth…
New Delhi, November 22, 2024: Dr. Gautam Kanodia has emerged as a visionary leader, redefining…
New Delhi, November 21, 2024: Over the years, Delhi-NCR has emerged as a hotspot for…
~ The Company strengthens the product portfolio with the launch of innovative & ‘Made in…
- NAREDCO Maharashtra and 1 Finance Unveils Comprehensive Study on Mumbai's Real Estate Landscape -…
The announcement marks a major step in offering Flexible Grade-A Office Solutions for Modern Businesses…