IRB Infra’s SPV Commissions Yedeshi – Aurangabad Highway

Mumbai, March 19, 2019: IRB Infra’s SPV, Yedeshi Aurangabad Tollway Pvt. Ltd. (YATPL), has partially commissioned its four laninghighway project Yedeshi to Aurangabad, in the State of Maharashtra, on March 17, 2019; thus, throwing open all four lanes for vehicular traffic.

The SPV is in possession of the Provisional Certification from the Competent Authority to commence tolling w.e.f. 17th March 2019, as it has completed 85.60% work of the project admeasuring 161.87 Kms, out of totallength of 189 Kms. of the Yedeshi – Aurangabad Section of NH-211. Accordingly, the SPV has started tolling on the project from 17th March 2019.

Speaking on the occasion, the Chairman & Managing Director of the Company  Mr. Virendra D. Mhaiskar said, “The newly widened highway will now have direct and quicker connectivity between two major cities of Maharashtra – Solapur and Aurangabad; thus further smoothening the connectivity between South and North India. We hope that it would bring a boost to the economy of the region as well as a good travelingexperience for both, passengers and goods transporters, with high safety”. He further added, “This is our third BOT project commissioned successively after Kaithal – Rajasthan Border Project in September 2017 and Solapur – Yedeshi Project in March 2018 and now Yedeshi – Aurangabad in March 2019; which demonstrates consistencies in project execution capabilities of the Company to bring better highway connectivity for developing India.”

Key features of the project:

  • Total project length 189.1 Kms section on NH 211. The stretch connects the prime places in the State including Tulajapur and Osmanabad.
  • NHAI awarded this project under DBFOT pattern to IRB Infra for converting existing 2 lanes into 4 lanes, at a Project cost of Rs. 3,370 Crores
  • Project has Viability Gap Funding of Rs. 558 Crores from the NHAI
  • The project will have service road of 73.71 Kms; 18 pedestrian underpasses; 5 flyovers; 5 major bridges; 57 small bridges; 98 intersections; 194 culverts; and one railway over bridge along with 3 Toll Plazas
  • The Concession period for project is 26 years
  • Tolling commenced w.e.f. March 17, 2019 midnight
  • COD achieved in line with provisional certification issued by the Competent Authority

Newsvoir

Recent Posts

Casagrand Continues its Aggressive Expansion in Hyderabad; Launches Its Fourth Project – Casagrand GS Infinity in Attapur

A landmark in ultra-luxury living, Casagrand GS Infinity offers 405 exquisitely designed 3 & 4…

23 hours ago

Gold, Cashback & Cheer: Festive Deals to drive homebuying surge this Akshaya Tritiya

New Delhi, April 26, 2025: Mumbai's real estate market is poised for a significant upswing,…

23 hours ago

ONE Group Developers to invest over ₹1,200 crore in Mohali for residential and commercial projects

The company will deploy the ₹1,200 crore investment over the next two years for project…

23 hours ago

Signature Global Secures ISO 31000:2018 Certification for Risk Management Excellence

New Delhi, April 26, 2025: Signature Global (India) Limited, one of India's leading real estate developers,…

23 hours ago

Housing.com Elevates Buyer-Seller Interaction with ‘Housing Chat’, Boosting Engagement 40X

Approximately 10% of Housing.com users actively utilise the chat functionality New Delhi, April 24, 2025:…

3 days ago

Max Estates takes over Delhi One project in Noida,under the aegis of IBC, adding sales potentialofINR 2,000 Crore and Annuity Rental of INR 120 Crore

Relief to homebuyers as Max Estates takes over ‘Boulevard Projects Private Limited (BPPL)’ to revive…

3 days ago