New Delhi, December 30, 2016: The Ministry of Statistics and Programme Implementation, Government of India has reported that out of 782 construction projects in India monitored by it, a total of 215 projects are delayed with the time over-run ranging from 1 to 261 months.The primary causes which are noted are delays in land acquisition, obtaining forest/environment clearances, tie-up of project financing, finalisation of detailed engineering, tendering, ordering and equipment supply, lack of infrastructure support and linkages, changes in scope, delay in tendering, ordering and equipment supply, law and order problems, geological surprises, pre-commissioning teething troubles and contractual issues.
Major impact of delays
1. Delays in projects have a direct bearing on the overall cost of construction. For example, from 2010 to 2015, the cost of cement (per bag) increased by 74%, steel increased by 34%, bricks increased by 69%, sand increased by 240% and skilled labour (on a per day basis) increased by 96%.It is therefore, understandable, that the cost overrun in delayed projects has resulted in approx 24.77% increase in the original cost of the projects,amounting to Rs. 1,09,359 crore.
2. Delays in a project also increase the likelihood of disputes between the parties and needless to say, these disputes may derail the project. The average duration for settlement of disputes is more than 7 (seven) years in India.
In light of the above, this article aims to provide a general overview of the categories of delays that should be borne in mind before executing agreements for a construction project.
Delay events in construction projects may be classified as excusable or in-excusable based on which party bears the cost and time implication of suchevents. For example, an event of force majeure which impacts the work of the contractor is generally considered as an excusable delay, whereas delays caused by the sub-contractors appointed by the contractor are regarded as inexcusable.
A critical delay in a construction project is considered as a time lag in the completion of workvis-à-vis the time period prescribed in the contract for its completion. During the entire duration of the construction project, there may be various reasons (as discussed above) which push forward the final completion of the project. These reasons for delay may be attributable to the owner or the contractor.
Concurrent delay events: A concurrent delay is most commonly defined as the occurrence of two or more critical events of delay, occurring concurrently and in parallel during the lifecycle of a project, one of which isattributable to the owner and the other to contractor.Thus, even if one delaying event is absent, the other would still delay the project. For example, if there is a delay of 90 days in start of construction because the owner has not given possession of the land to the contractor, and if during this 90 day period, the contractor also fails to mobilise resources, such delay would be considered as a concurrent delay.
In certain projects a situation may arise where two or more delaying events may arise at different times and impact the same work to be performed. If one of the delaying events is attributable to the owner and the other to contractor, such delays are deemed to have a concurrent effect on the projectand would also be considered as concurrent delay events.
How do contracts factor in the delays!
The manner in which the parties deal with the different kinds of delay events depends entirely on the contractnegotiations between parties. Most contracts allow a contractor to receive additional time for delays attributable to the owner. However, the right of the contractor to claim compensation for such delay is limited. Au contraire, if the delay is attributable to the contractor, the owner is generally entitled to seek liquidated damages and the contractor does not receive any extension of time or compensation.
With respect to the other kinds of delay, the contracts do not generally address the issues of concurrent delay events and/or pacing delays. It is pertinent to mention that certain specific language in the contract like, ‘time is of the essence’, may even be interpreted to argue that the contractor is under an obligation to expedite the completion of the work and mitigate its losses. This lack of an express understanding between the parties is quite unfortunate since it, more often than not, leads to disputes.
Parkinson’s Lawand the old adage ‘time is money’ are most apt for the construction industry.Therefore, it is important for the project stakeholders to understand the risks in a construction contract and identify the possible delays in the project lifecycle. This should enable the contractor to notify the owner, seek clarifications (where needed) and open a dialogue to ensure that the project remains on schedule and risks related to litigation, cost and time over-runs are mitigated.
Corporate Comm India(CCI Newswire)
New Delhi, November 21, 2024: Over the years, Delhi-NCR has emerged as a hotspot for…
~ The Company strengthens the product portfolio with the launch of innovative & ‘Made in…
- NAREDCO Maharashtra and 1 Finance Unveils Comprehensive Study on Mumbai's Real Estate Landscape -…
The announcement marks a major step in offering Flexible Grade-A Office Solutions for Modern Businesses…
Considered as hot investment opportunity for the real estate enthusiasts, Studio apartments present several advantages…
New Delhi, November 18, 2024: As Indian cities grapple with rapid urbanization, evolving lifestyles, and…